🏭Manufacturer since 1987 · 3 production bases: Hangzhou · Weihai · Wuhu
Home›Resources›News & Exhibitions›Zimbabwe gold mine: three lines in three batches, then one spare screen
Customer story

Zimbabwe gold mine: three lines in three batches, then one spare screen

A mine owner in Gweru, Zimbabwe commissioned three crushing lines in three separate purchase rounds, all on Shuangjin machines. His fourth order contained no crushers at all — just one vibrating screen, bought to sit in the warehouse as a standby unit. The arithmetic behind that decision is worth reading for anyone running an overseas project.

3 November 2026Published
Customer storyCategory

Buying equipment for a mine outside your own country is a pickier business than buying at home. Not because of the price — because of what happens on the day a machine stops. Can you afford to wait?

Three production lines, assembled in three batches

The mine is in Gweru, in Zimbabwe’s Midlands province. The owner handles his own blasting and controls his own feed, and from the first machine onward he has bought nothing but Shuangjin equipment — jaw crushers, spring cone crushers and vibrating screens — across three separate purchase rounds that now form three complete crushing lines.

These were not single-signature turnkey orders. They were added batch by batch over three years: the first line proved itself on site, then the second and third followed. Lines one and two each run one SJ.E.75.10 jaw crusher with one SJ.1650 spring cone crusher. Line three runs one SJ.E.90.12 jaw crusher with two SJ.1650 spring cone crushers.

For screening, all three lines use the same unit: the SJ.2.Y.A.30.60 circular vibrating screen.

Buying in three batches says something in itself. This was not a single all-in bet. It was use it, verify it, then commit more. Overseas projects mean long freight and a long service radius, and a customer who keeps coming back is voting with the operating record of the previous order.

SJ.Y.A series circular vibrating screen on a Zimbabwe gold mine, showing the double-deck screen box and exciter assembly
Figure 1 — An SJ.Y.A series circular vibrating screen; the double-deck screen box and exciter assembly are clearly visible.

The fourth order: one screen, nothing else

The contract was signed in July this year and the shipment completed in October. Unlike the previous three rounds, this one contained no crushers. It was a single SJ.2.Y.A.30.60 vibrating screen, ordered explicitly as a standby: it goes straight into the warehouse on arrival, and if any screen on the lines fails, it is lifted out and swapped in immediately.

That is uncommon among mines in China. When a screen fails there, most operators book a repair and wait for parts; very few buy a complete machine to keep in the warehouse. Here the arithmetic is simple. Three lines run at once. If one screen goes down, the material coming out of the jaws and cones backs up and the whole line stops. In Africa, waiting for a critical spare part is measured in weeks.

Buying a spare screen is really buying the production from those weeks of waiting — not just a faster repair.

SJ.E series jaw crusher installed on a Zimbabwe gold mine, showing the twin flywheels and tension rod springs
Figure 2 — SJ.E series jaw crusher, showing the twin flywheels and the tension-rod springs.

Same model on all three lines, so one spare covers everything

One detail made the single spare possible, and it is easy to miss: all three lines use the same screen model. That standby unit will fit any of them — the mounting holes line up, so it can be lifted in and started without reworking foundations or adapting anything.

One spare, three lines covered. Had each line used a different screen model, the owner would have had to stock one of each — or give up on the idea entirely, because there would be no way to know which one to keep. Standardised selection is what makes “just one spare” work.

Two SJ series spring cone crushers installed side by side on a Zimbabwe gold mine
Figure 3 — SJ series spring cone crushers, two units installed side by side.

It also shows where the value sits in his calculation. A vibrating screen runs under continuous high-frequency vibration; it is a high-load, wear-prone machine, and when it fails you cannot afford to wait. So one complete unit sits ready. The purpose of the repeat purchase is not a faster repair — it is keeping the line from stopping at all.

For export business, the repeat order is the hardest proof

The hardest part of selling equipment overseas has never been the first order. It is the second and the third. A first order can be won with a quotation and a specification sheet. From the second order onward, what wins it is the reputation the machine has built on a mine site, year after year.

This customer in Zimbabwe came back three times, and his fourth purchase was still inside the same system, still a vibrating screen. That is not an impulse buy. It is three years of site operation and three production lines running continuously, verifying for himself that Shuangjin equipment suits African gold-mine conditions.

Export is not one or two deals — it is repeat business, customer by customer

The Zimbabwe customer is one square on Shuangjin’s export map.

In Africa, more than 200 mines and crushing lines now run Shuangjin equipment — from East Africa to West Africa, spring cones, jaw crushers and screens working across different kinds of mine. In Indonesia, an owner who went there to invest in an aggregates project replaced six foreign-brand multi-cylinder hydraulic cones with two Shuangjin units. And in Zimbabwe, one of the continent’s established mining countries, a complete line shipped out early this year — feeder, jaw crusher, cone crusher and screen, supplied as one package.

Equipment export is not built on a single transaction. It is built on trust accumulated one machine at a time, one repeat order at a time.

SJ.Y.A circular vibrating screen loaded on a truck for shipment, multi-deck screen box visible
Figure 4 — An SJ.Y.A circular vibrating screen loaded for shipment, with its multi-deck screen box clearly visible.

Running a gold or aggregates project on the continent and weighing up standby capacity? Send us your flow sheet, feed size and target tonnage — we will come back with a configuration, a spare-parts list and the lead time for each item.

Published 3 November 2026 · Customer story. Compiled by the Shuangjin export team from project records for this customer.

A question this article does not cover?

Ask us directly. If it is a question we are asked often, it becomes the next article — and you get the answer either way.

Get a Quote WhatsApp